Management Report February 2015

MANAGEMENT REPORT COFFEE CREEK CONDOMINIUM ASSOCIATION February 25, 2015 Financials: As of today February 25, 2015 Cash on Hand $21,810.14 Savings Account $3,357.88 General reserve $128,814.64 Insurance reserves $79.08 Total Liabilities/Equity $154,061.74 Delinquencies: As of February 17, 2015 there are 12 delinquent accounts. Delinquent percentages are up from […]
Minutes Feb. 25, 2015

Coffee Creek Homeowner’s Association Meeting Minutes, Board of Directors February 25, 2015, 6:00 pm – Coffee House Call to Order: 6:04 pm by Phyllis Palmer, President Quorum established. Board Members Present: Rita Senecal #38, Joyce Warner #41, Phyllis Palmer #34, Petra Lippa #43, Shawn Walker #46, Rob Cooper, #47 […]
Minutes Jan. 22 2015

Coffee Creek Homeowner’s Association Meeting Minutes, Board of Directors January 22, 2015, 6:00 pm – Coffee House Call to Order: 6:04 pm by Phyllis Palmer, President Quorum established. Board Members Present: Rita Senecal #38, Joyce Warner #41, Phyllis Palmer #34, Petra Lippa #43, Shawn Walker #46 […]
Managers Report January 22, 2015

MANAGEMENT REPORT COFFEE CREEK CONDOMINIUM ASSOCIATION January 22, 2015 Financials: As of year end – December 31, 2014 (January 2015 Financials not available at this time) Cash on Hand $2,430.28 Savings Account $8,095.03 General reserve […]
Managers Report Nov 25, 2014

MANAGEMENT REPORT COFFEE CREEK CONDOMINIUM ASSOCIATION November 25, 2014 Financials: As of month end – October 31, 2014 the association has $156,651.53 in assets Operating account $51,269.54 General reserve $86,970.73 Insurance reserves $18,411.26 Delinquencies: As of November 24h there is a total of $33,296.29. owed to the association, which […]
Agenda October 28, 2014

Agenda October 28, 2014 Call to Order Establish a Quorum Approval of September Minutes Financial Report Management Report Old Business Dryer Vent Cleaning Report New Business Storage Shed Repair Fence Repair Open to the Floor
Agenda

Agenda September 30 2014 Call to Order Establish Quorum Approval of August Minutes Financial Report Management Report Old Business Dryer Vent Cleaning Garage Doors Front Doors New Business Gutter Cleaning Security Cameras 55+ Community Open to the Floor
Agenda August 26, 2014

Call to order Establish a quorum Approval of July minutes Financial Report Management report OLD BUSINESS Outside lights RV shed Post at unit 8 Deck railings – Rob NEW BUSINESS Sprinkler system repair Fence Repair Dryer vent cleaning Roofs – Garages & porches, Coffee House
July 29 HOA Agenda

Agenda July 29, 2014 Call to Order Establish a Quorum Approval of June Minutes Financial Report Management Report Old Business Lights Deck Railings – Rob New Business Pool & Dock Signs Dryer Vent Cleaning Roofs – Units 41 & 44 – 7 thru 10 Open to the Floor
Gutter Replacement

Several proposals for replacing all of the gutters at Coffee Creek Condos were reviewed at the Board meeting on June 24, 2014. The proposal from Advance Custom Gutters for $18,130 was approved by the Board. Work started last week and is expected take another three weeks as the contractor is working 2-3 days/week at Coffee […]